The head of the Defense Council of Kryvyi Rih, Oleksandr Vilkul, accused ArcelorMittal Kryvyi Rih of shutting down the plant for economic reasons and using Russian missile attacks to explain the decision. He shared this view in a comment to the Financial Times. The management of Ukraine’s largest mining and metallurgical complex, meanwhile, links the shutdown to damage to production facilities and the threat to people’s lives.

According to Vilkul, the plant contributes about 30% of the city budget. He criticized the company’s decision:

“Nowhere in Ukraine is safe. In reality, they’re doing this for economic reasons,” said Oleksandr Vilkul.

The plant’s CEO, Mauro Longobardo, told journalists that the shutdown decision was made in September, after strikes damaged two blast furnaces—the last ones still operational. He explained that these units were the foundation of pig iron production.

“We simply depend on whether someone else decides that our people should go to work today and die,” said Mauro Longobardo.

In a statement dated September 25, 2026, the company had already explained that it could not safely and reliably resume operations at the plant. At the time, it said it was discussing the plant’s future with the government of Ukraine and intended to preserve its infrastructure to keep open the possibility of resuming production in the future.

Against the backdrop of key industrial enterprises shutting down, Vilkul also said that the city budget needed to be cut and some development projects abandoned as a result. He linked this to lower production and tax revenues. The city said its priority was to fund essential needs.

On October 10, ArcelorMittal Kryvyi Rih began placing the plant into cold shutdown mode. This followed four Russian missile attacks that killed 6 employees and injured 18 others. Primary steel production came to a halt.

After the process began, the Kryvyi Rih City Council called for the plant to remain open. Its appeal emphasized the risk of job losses and environmental hazards.

According to Longobardo, the shutdown process will continue until December. Once it is complete, the company plans to operate as follows:

  • Only about 1,500 employees will be needed to keep the plant operational.
  • The remaining 14,500 employees will be sent home but will remain on the payroll and receive two-thirds of their salary.

The CEO insists that the company does not plan to leave Ukraine. At the same time, he acknowledged that even the end of the war would not resolve the uncertainty surrounding the plant’s future. After a year in cold shutdown, significant investment would be needed to restart production.

A prolonged shutdown also poses a staffing risk: the plant could lose its most highly qualified employees, who may have to look for work elsewhere.